timeline
Dedication to relentless progress in the name of Ingham & Co.
2024
Designed with big operatrional footprints in mind.
Ingham Property Group was the first organisation to be granted a master planning pathway by the State Government. Complying Development pathways fast-track the approval process to an average of 30-35 days.
Endeavour Energy Bradfield North 90MW substation civil works complete March 2024.
Master Plan Technical Assurance Panel Process concludes April 2024. Endeavour Energy’s Bradfield North 90MW zone substation construction underway May 2024.
2025
Master Plan approved on 11 July 2025 unlocking Complying Development Pathway July 2025.
Commissioning of Bradfield North Zone Substation Q4 2025.
2026
Stages 1 and 2 civil and building works underway 2026.
Civil site works commenced January 2026
Commissioning of Bradfield North Zone Substation Q1 2026
Commence construction of Badgerys Creek Road Roundabout Q2 2026
2027
Completion and commissioning of new facilities Q4 2027
OUR SITE

This precinct provides the ideal foundation for businesses looking for planning certainty ahead of investing in the future.

LAND

184ha+

Total site area within the Aerotropolis Core Precinct
LOT SIZING

0-20ha

Accommodates operational footprints on lots from 1 hectare up to 20 hectares
ZONING

Enterprise Zoned

Approved for activation